After nine days of installation, the Malta cold room project has been successfully completed. The cold room structure, insulated floor, refrigeration units, sliding door, temperature control system, and electrical connections are all in place. The system has been tested and is operating at ...
-
Day 8 of the Malta cold room project is making steady progress. Today, our team focused on installing the insulated floor panels, completing the electrical connections, and testing the refrigeration control system. The evaporator units and insulated piping were also carefully checked to ensure ...
-
Day 7 of the Malta cold room project is progressing smoothly. Today, our team focused on installing the evaporator units, connecting the refrigeration pipes, and completing the control box installation. At the same time, we continued working on the cold room door frames and related finishing details...
-
Day 6 of the Malta cold room project is moving forward. Today, our team focused on installing and adjusting the cold room doors, fitting the door hardware, and assembling the evaporator units. Using lifting equipment, every component was carefully positioned and secured to ensure proper installation ...
-
Day 5 of the project is well underway in Malta. Today, our team focused on connecting the refrigeration equipment, welding the copper pipes, and completing the insulation work. We also continued installing the evaporators and finishing the cold room panels. Every pipe, connection, and detail matters ...
-
On the fourth day, the main cold room structure became more complete, and the refrigeration equipment began to be installed inside the room. The installation team continued working on ceiling panel assembly, joint treatment, and edge alignment. Scissor lifts and a forklift were used to support the ...
-
On the third day, the installation moved into the ceiling panel assembly and refrigeration equipment preparation stage. The team used aerial platforms and a forklift to move, position, and assemble the ceiling panels. As the roof panels gradually came together, the internal space and overall ...
-
The main installation work continued on the second day. Forklifts and aerial platforms were used to support the installation team as they moved, positioned, and assembled the cold room panels. The wall and ceiling panels are gradually coming together, forming the main structure of the cold room. ...
-
Malta Cold Room Project | Day 1 The Malta cold room project has officially started. On the first day, our installation team completed site measurements, work area preparation, material handling, and initial cold room panel positioning. Every laser line and every measurement is carefully checked to ...